emeadaxsupport: How General Budget Reservations will update Committed Cost on Project Contracts
Источник: http://blogs.msdn.com/b/axsupport/ar...contracts.aspx
==============

This article will explain how to create a General Budget Reservation for tracking Committed Cost on a Project.

This article assumes that you have installed KB3047235 on an AX 2012 R3 CU8 environment and you are using public sector. It also assumes you have gone through all the initial setup required that are listed in MSDN article: https://msdn.microsoft.com/en-us/dyn...92460(v=ax.60)

In the Project Management and Accounting Parameters you will need to make sure to include General Budget Reservations with Committed Cost. Project Management and Accounting | Setup | Project Management and Accounting Parameters

1. Click the Cost Control Option
2. Mark General Budget Reservation checkbox


3. Close the form

Create a Budget Register Entry to track your budget – Budgeting | Common | Budget Register Entries | All Budget Register Entries – In the Budget Register Entry tab, in the New group, click the Budget Register Entry button.

1. Select your Budget Model
2. Select your Budget Code



3. Click the Add Line button
4. Select the Account Structure
5. Enter the Dimension Values
6. Enter the Amount



7. In the Budget Register Entry tab in the Update group click the Update Budget Balances button
8. Click Ok if prompted
9. Close the Infolog
10. Close the Budget Register Entry form

Create a new Project – Project Management and Accounting | Common | Projects | All Projects – In the Project tab in the New group click the Project button

1. Select the Project Type
2 Enter the Project Name
3. Select the Project Group
4. Select a Project Contract ID or Create a new one



5. Click Ok button
6. Click the Project Contract ID link
7. Expand the Funding Limits fast tab
8. Click the Add button
9. Select a Funding Source
10. Select a Project
11. Enter an Amount



12. Close the Projects Contract form
13. In the Projects form in the Project tab in the Maintain group click the Project Stage button and select In Process
14. Click Ok if Prompted
15. Close the Project form

Create a General Budget Reservation to link to the Project you created – Budgeting | Common | General Budget Reservation | All General Budget Reservation – In the Budget Reservation tab in the New group click the Budget Reservation button

1. Select Reservation Type: Make sure the reservation time is relieving on the PO
2. Enter Reservation Title
3. Enter the End date




4. Click Ok
5. Click the Add Line button
6. Enter the Transaction Text
7. Select the Project you created above
8. Change the Category if needed
9. Enter the Quantity
10. Enter the Unit Price



11. Expand the Line Detail fast tab
12. Select the General tab
13. Select the Procurement Category



14. Click the Project tab
15. Select the Unit



16. Save the record
17. Click the Distribute Amounts button
18. Verify the Ledger Account matches the Ledger Account matches the Budget Register Entry



19. In the Budget Reservation tab in the Post group click the Budget Reservation button
20. Close the Budget Reservation form

Go back to the Project Contract for this project.

Note the Committed Amount -




In the Control tab in the Control group click the Committed Cost button.

You can see the General Budget Reservation has a cost amount.



If you click on the General tab you can see the General Budget Reservation that is linked.




Now create a Purchase Order for this project – In the Project form in the Manage tab in the New group click the Item Task button and select Purchase Order

1. Select the Vendor Account
2. Click Ok
3. Select the Procurement Category that was referenced above
4. Enter Quantity
5. Enter Unit
6. Enter Unit Price



7. Expand the Line Details fast tab
8. Select the General Budget Reservation created above



9. Save the record
10. In the Purchase tab in the Generate group click the Confirm button

Now go back to the Project Contract, check the funding source and the Committed Cost form.

Note the Committed Amount does not change



In the Committed Cost form we can see there is a record for our Purchase Order and the Amount of Cost on the General Budget Reservation is reduced by the amount of the PO.



Now invoice part of the Purchase Order – In the Purchase Order form in the Invoice tab in the Generate group click the Invoice tab

11. Enter the Number
12. Change the Quantity to be less than the full amount




13. In the Vendor Invoice tab in the Actions group click the Post button

Go back to the Project Contract for the Project.

Note the Spent Amount is update and the Committed amount is reduced.



The Cost Amount on the PO is reduced by the amount of the vendor invoice.



The General Budget Reservation will hold the cost until it is relieved by the Purchase Order, which will then transfer the cost from the General Budget Reservation to the Purchase Order.




Источник: http://blogs.msdn.com/b/axsupport/ar...contracts.aspx
__________________
Расскажите о новых и интересных блогах по Microsoft Dynamics, напишите личное сообщение администратору.
 

Похожие темы
Тема Автор Раздел Ответов Посл. сообщение
crminthefield: Podcast and Overview: Microsoft Dynamics CRM 2011 Update Rollup 15 Blog bot Dynamics CRM: Blogs 1 10.02.2016 10:26
crminthefield: Podcast and Overview: Microsoft Dynamics CRM 2011 Update Rollup 17 Blog bot Dynamics CRM: Blogs 0 10.05.2014 06:30
crminthefield: Podcast and Overview: Microsoft Dynamics CRM 2011 Update Rollup 16 Blog bot Dynamics CRM: Blogs 0 23.01.2014 03:15
crminthefield: Podcast and Overview: Microsoft Dynamics CRM 2011 Update Rollup 14 Blog bot Dynamics CRM: Blogs 0 12.07.2013 07:13
crminthefield: Podcast and Overview: Microsoft Dynamics CRM 2011 Update Rollup 13 Blog bot Dynamics CRM: Blogs 0 27.03.2013 22:12

Ваши права в разделе
Вы не можете создавать новые темы
Вы не можете отвечать в темах
Вы не можете прикреплять вложения
Вы не можете редактировать свои сообщения

BB коды Вкл.
Смайлы Вкл.
[IMG] код Вкл.
HTML код Выкл.
Быстрый переход

Рейтинг@Mail.ru
Часовой пояс GMT +3, время: 16:08.